Prompt Payment Act Damages

posted by Michael Fortney  |  Dec 14, 2009 4:47 PM in Construction Law


The prompt payment law requires contractors to pay lower tier subcontractors or suppliers that portion of the payment to the contractor that represents the work done by the contractor or the supplies provided by the supplier, minus retainage, within ten days of receiving payment for the lower tier subcontractor's work. Ohio Rev. Code 4113.61.

Complying with statutory prerequisites

In order to succeed in a claim under the prompt payment law, the subcontractor or materialman must:

  1. have a valid and enforceable contract claim;
  2. have submitted an accurate invoice to a contractor for payment for work or materials, allowing the contractor a sufficient time to include the invoice in the contractor's invoice to the owner;
  3. establish that the contractor was paid for the invoice submitted after the submission of the subcontractor's or materialman's invoice;
  4. establish that the owner paid money to the contractor for work completed by the subcontractor or for materials delivered by the materialman;
  5. establish that the contractor has refused to timely pay the subcontractor or materialman an amount equal to the percentage of completion allowed by the owner; and
  6. establish that there is no valid reasons for the contractor to withhold any amount necessary to resolve disputed claims involving the work or materials.

Damages available under the prompt payment law

A subcontractor or materialman may recover interest at 18% per annum, costs, and attorneys fees, in the event that a violation of the prompt payment law is established.


Revision History

Most Recent Articles

Ohio Court of Appeals Clarifies Time for Serving Notice of Furnishing under Mechanic's Lien Law In a case litigated by Michael L. and Michael R. Fortney of Stark & Knoll, the Court of Appeals for Ohio’s Ni ...
NLRB Declares Chipotle Company Policies Unlawful An Administrative Law Judge (ALJ) for the National Labor Relations Board (NLRB) issued her ruling in the Chipotle case ...
Ohio Court of Appeals Upholds Arbitrator’s Authority When Arguably Construing or Applying Contract A recent ruling by the Ninth District Court of Appeals ruled that a trial court cannot vacate an arbitration award beca ...
Ohio Supreme Court Upholds Liquidated Damages Provisions in Construction Contracts The Ohio Supreme Court overturned the Fourth District Court of Appeals' holding that a $700 per day liquidated dama ...
2nd Circuit Agrees with NLRB; Facebook "like"s are Protected Activity In 2014 the National Labor Relations Board (NLRB) issued its ruling in  Triple Play Sports Bar . It decided that&n ...